同学,Fixed overhead volume capacity variance is the difference between budgeted (planned) hours of work and the actual hours worked, multiplied by the standard absorption rate per hour. 预计小时与实际小时之间的差异,实际小时大于预计小时,就是在花费一定FOH的,实际生产的时间更长,有利于公司的,是F。 Fixed overhead volume efficiency variance is the difference between the number of hours that actual production should have taken, and the number of hours actually taken (that is, worked) multiplied by the standard absorption rate per hour.实际的产量下应该的小时和实际的小时之间的差异,实际大于预计,说明同产量下实际时间过长,效率不高,对公司是不利的,是A。
The real talent is resolute aspirations.
真正的才智是刚毅的志向。
追问12023-03-03 19:25
老师,意思是capacity是时间长,相对产量也多,所以实际>预计是对公司有利, 但efficiency是同一“产量”,耗时长反而对公司不利,可以这样理解吗?
回答2023-03-06 09:52
同学,是的。